Panel Approves $19,103.50 Final Project Warrant
The Stoneham School Building Committee approved a $19,103.50 warrant for final project invoices and set a Nov. 18 soft opening for a new wetlands trail.
The Stoneham School Building Committee approved a $19,103.50 warrant for final project invoices and set a Nov. 18 soft opening for a new wetlands trail.
The Watertown School Building Committee voted unanimously to authorize design and bidding on the city's new middle school, following a City Council vote to move the project forward.
The Lexington School Building Committee learned the state Department of Environmental Protection affirmed the town's wetlands order for the Lexington High School rebuild without changes, and no appeal had surfaced as of the October 19 meeting.
Stoneham's new high school hits 99 percent completion as Building Committee clears $430,000 in invoices.
Lexington School Building Committee votes unanimously to submit its 60% design to the state. Vice Chair Mike Brunner reported the design estimate, checked independently by A.M.
Watertown's School Building Committee approved $1.8 million in high school invoices and a drainage and safety change order.
Lexington School Building Committee locks in cheaper field house track design as DEP wetlands appeal risks up to $20 million in added costs.
Watertown's new high school cleared final inspections ahead of a September 8 student move-in date.
The Watertown School Building Committee approved a $221,432.05 change order for the high school, even though the building still lacks a certificate of occupancy.
Stoneham School Building Committee settles branding wall dispute, reports LEED Gold.