Lincoln authorizes up to $100,000 for ledge blasting at community center site Lincoln's community center project hit ledge, and the building committee approved blasting to remove it.
Lincoln Panel Rejects $1,331 Partition Credit, OKs $30,000 Bridge Fix Lincoln building panel rejects contractor's partition credit, presses ahead on $30,000 bridge fix.
Lincoln panel approves $323,000 in community center cost increases Lincoln Community Center Building Committee approves $323,000 in cost increases as project runs four months late.