Committee Approves PA System, Ledge-Blasting Changes
Lincoln's Community Center Building Committee approved two contract changes and declined to set a firm opening date.
Lincoln's Community Center Building Committee approved two contract changes and declined to set a firm opening date.
Lincoln's Community Center Building Committee approved $19,030 in net change orders while blasting contractor Hutter Construction over a schedule that has slipped toward January 2027.
Lincoln's community center project hit ledge, and the building committee approved blasting to remove it.
Lincoln building panel rejects contractor's partition credit, presses ahead on $30,000 bridge fix.
Lincoln Community Center Building Committee approves $323,000 in cost increases as project runs four months late.