Committee approves $558,608 high school change order

The School Building Committee approved a $558,608 change order for the new Watertown High School.

Email Text Facebook X

School Building Committee · Meeting of January 21, 2026

WATERTOWN — The School Building Committee approved a $558,608 change order for the new Watertown High School. Members voted 8-0 on Change Order No. 28, which covers a second-floor dining seating area, two added security cameras, a rooftop medical call button, solar equipment work and dishwasher ground-fault protection. The remaining list of potential changes stands at about $1.6 million against a $201.461 million MSBA budget.

A project team presenter said contractor Brait Builders now projects substantial completion on May 1, with move-in "the last day of school and a couple days thereafter in June." The committee also approved a $21,000 final Lowell Elementary invoice and $1,452,177.61 in Brait Builders payment, with the contractor 93 percent complete. Planning & Community Development Head Steve Magoon was thanked ahead of his end-of-January retirement.

In the full story:

  • The Full Story
  • Why It Matters
  • Key Motions & Votes
  • Source
  • Watertown's community access TV: School Building Committee meeting, January 21, 2026
  • The complete report: 925 words

Source: the School Building Committee meeting of January 21, 2026, reported from the official video recording and transcript.

Checked against the record: before publication this article was automatically compared with the meeting transcript.

Share this story

Email Text Facebook X

Know someone in Middlesex County who follows town government? Share Townbrief Middlesex County: they can sign up free.

Share this story

Email Text Facebook X

Anyone can open a shared story. Members' stories show the free part and a sign-up line to people who are not members.